Crossan Park Tennis Court Upgrades
91 Parsons Road, Landenberg, PA 19350
Court Closure – Tentative Dates
Work is Weather Dependent
There will be several steps to the upgrades:
Step 01 - Removal of the fence that separates the two courts. The poles will remain in place.
Step 02 - Repair of the large crack the separates the two courts. The courts were built at different times.
Step 03 - Pressure washing, cleaning, repair of cracks in the courts and color coating of the courts.
Step 04 - The fence between the two courts will be reinstalled.
Here are some tentative dates that the tennis courts will be closed. Check back often for updates.