Crossan Park Tennis Court Upgrades

91 Parsons Road, Landenberg, PA 19350
Court Closure – Tentative Dates
Work is Weather Dependent

 

There will be several steps to the upgrades:

 

Step 01 - Removal of the fence that separates the two courts.  The poles will remain in place.
Step 02 - Repair of the large crack the separates the two courts.  The courts were built at different times.
Step 03 - Pressure washing, cleaning, repair of cracks in the courts and color coating of the courts.
Step 04 - The fence between the two courts will be reinstalled.

 

Here are some tentative dates that the tennis courts will be closed.  Check back often for updates.

 

Step 01 – Is scheduled to occur on June 23rd / June 24th or June 28th.
Step 02 – To be scheduled
Step 03 – To be scheduled
Step 04 – To be scheduled
 