2023 Road Program Schedule

Notice to Residents on

Paving of Old School House Road

Subject: 2023 Franklin Township Road Program

Old School House Road Update - July 7, 2023

Franklin Township has contracted with Long’s Asphalt to complete the Township’s 2023 Road Program. We are providing this notice as an update to progress of the work completed to date, and also the schedule for the final paving. The Road Reconstruction, embankment grading and surface milling has been completed. The final paving will be completed next week. The schedule is outlined below.

Monday 7/10 – Final grading of areas that were reconstructed.

Tuesday 7/11 – Complete Base Repair of designated areas and place binder course on reconstructed areas. We will be completing repairs on both ends of Old School House Road access to and from properties could be delayed.

Wednesday 7/12 – Place final wearing course on Roadway starting at Wickerton Road and Paving towards Pheasant Hill Lane. (We will finish the day just South of Pheasant Hill Lane. Residents should plan on using the Chesterville Road access for most of the day unless the paving operation has passed your residence.) The final wearing course will be completed in 1 pass.

Thursday 7/13 – Place final wearing course on Roadway between Pheasant Hill Lane and Chesterville Road. (Residents should plan on using the Wickerton Road access point for the day. Residents at the southern end of Old School House Road access will be determined by the location of the paving operation.

The final wearing course will be completed in 1 pass.

Work hours will be from 7:00 am to 5:00 pm Monday through Friday. During the duration of the work the road will be closed to through traffic. We appreciate your understanding and patience as we complete the road improvements.

It is important that you allow extra time into your daily schedules.   You will be inconvenienced while we improve Old School House Road, and we are sorry.  Residents should plan on leaving their residence before the paving process starts if they must go out or plan on staying home for the day.  Work hours will start at approximately 7:00 AM and end at approximately 5:00 PM, Monday through Friday.  Using a single pass paver removes the cold joint (center seam) in the road, thus improving the longevity of the road.  Please look for direction from the flagger on duty before proceeding.

 

Example of Single Pass Paver

(Photo for Illustration Purposes Only)

We are asking that you please pass this information along to anyone you know who travels these roads.  This will include friends and family, your favorite delivery people, house cleaners, and trash companies.  Emergency Services (911) has been alerted to our schedule and if an emergency occurs, we will allow them to proceed without hesitation.  Please encourage them to subscribe to our social media pages.  We will update these pages as developments and revisions as needed.

Long's Paving has delivered a letter today to each homeowner on Old School House Road and Pheasant Hill Lane. 

__________

Revised Road Program Schedule

June 28, 2023

Scroll through the entire screen to learn about single pass paving.  We are sorry for the inconvenience that this will cause. 

It will be a much better road at the end of the day as the center seam will be eliminated.

Our Contracted needs to adjust the paving schedule for Old School House Road.   They pushed the paving 1 day to give them time to Fine Grade.

Wednesday 6/28 – Pave Hess Mill Road (1 pass paving where possible) and Install Leveling Course on Ways Run for Superelevation of section of Road.  Continue Embankment Grading on Old School House Road.

Thursday 6/29 – Pave Ways Run and Johnson Lane (1 Pass Paving).  Shoulder and embankment grading Old School House Road.

Friday 6/30 – Shoulder and embankment grading Old School House Road.

Wednesday 7/5 Embankment seeding and netting.

Thursday 7/6 – Embankment seeding and netting.

Friday 7/7 – Embankment seeding and netting.

Monday 7/10 – Fine Grade areas that were re-profiled on Old School House Road.

Tuesday 7/11 – Base Repair and Place Binder Course Old School House Road (1 pass paving).

Wednesday 7/12 – Pave Old School House Road (1 Pass Paving).

Thursday 7/13 – Pave Old School House Road (1 Pass Paving)

 

Revised Road Program Schedule

June 27, 2023 - 11:17 AM

Wednesday 6/28 – Pave Hess Mill Road (1 pass paving where possible) and Install Leveling Course on Ways Run for Superelevation of section of Road.  Continue Embankment Grading on Old School House Road

Thursday 6/29 – Pave Ways Run and Johnson Lane (1 Pass Paving).  Shoulder and embankment grading Old School House Road

Friday 6/30 – Shoulder and embankment grading Old School House Road.

Wednesday 7/5 Embankment seeding and netting.

Thursday 7/6 – Embankment seeding and netting

Friday 7/7 – Embankment seeding and netting.

Monday 7/10 – Base Repair and Place Binder Course Old School House Road (1 pass paving).

Tuesday 7/11 – Pave Old School House Road (1 Pass Paving).

Wednesday 7/12 – Pave Old School House Road (1 Pass Paving).

 

 

 

Road Program Schedule Update - June 27, 2023

Weather Delay

 

The Township just heard from Long's Paving.  Due to the rains last night, work has been postponed and will be pushed one day back.  We are sorry for the inconvenience.  Once we receive an updated schedule, we will be sure to post it here and on our social media pages immediately.

 

Road Program Schedule Update - June 26, 2023

Ways Run and Johnson Lane

 

Franklin Township has contracted with Long’s Asphalt to complete the milling and paving for the Township’s Road Program. The work on the roads were delayed one day due to inclement weather. The Surface Milling of the roadway will be completed today, 6/26/23. The leveling course to super-elevate a section of Ways Run Road between 7 Ways Run Road and 11 Ways Run Road will take place on Tuesday 6/27/23 late morning or early afternoon. During this process there will be one lane of traffic and residents can expect some delays in this area. The final surface course will be installed on Wednesday, 6/28/23. The Township has requested the Roads to be paved in one pass. Our paver can pave roads up to 22’ wide in one pass, most Townships prefer 1 pass paving where applicable because it eliminates the center seam on the road (center seams tend to open up over time causing the road to deteriorate quicker) and provides a better finish product. Long’s Asphalt will start paving in the Cul-de-sac at 7:00 am on 6/28/23. Once we exit the cull-de-sac vehicles will not be able to get around the paving operation. During the paving process the residents will not be able to access their driveways or be able to drive on the roads. Residents should plan on leaving their residence before the paving process starts if they must go out, or plan on staying home for the day. Once more, the paving will take place on 6/28/23. Hours of operation are 7:00 am to 5:00 pm. There will be no parking on the roads during working hours. Also, the work schedule could be affected by inclement weather so the schedule could fluctuate a day or two. We appreciate your understanding and patience as we complete the road improvements.

If you would like to download this letter, please click here.

 

IMPORTANT 2023 Road Program Schedule Update

Single Pass Paver Information - Please read thoroughly!

 

Franklin Township has been updated by our Contractor regarding our 2023 Road Program Schedule.  As always, this schedule could fluctuate a day or two due to unforeseen weather- or job-related delays.  Please pass this information to anyone you know who may travel these roads.  Please be sure to subscribe to our social media pages.

Monday 6/26 – Complete Milling on Ways Run and Johnson Lane.  Continue Road Profiling and Shoulder Grading on Old School House Road.

Tuesday 6/27 – Pave Hess Mill Road and Install Leveling Course on Ways Run for Superelevation of section of Road.  Continue Embankment Grading on Old School House Road

Wednesday 6/28 – Pave Ways Run and Johnson Lane.  Shoulder and embankment grading Old School House Road.

Thursday 6/29 – Shoulder and embankment grading Old School House Road.

Friday 6/30 – Shoulder and embankment grading Old School House Road.

Monday 7/3 – Embankment seeding and netting.

Wednesday 7/5 Embankment seeding and netting.

Thursday 7/6 – Fine Grade Old School House Road.

Monday 7/10 – Pave Old School House Road.

Tuesday 7/11 – Pave Old School House Road.

 

Single Pass Paver Information - Originally Posted on June 15, 2023 - IMPORTANT

We are asking that you please pass this information along to anyone you know who travels these roads.  This will include friends and family, your favorite delivery people, house cleaners, and trash companies.  Emergency Services (911) has been alerted to our schedule and if an emergency occurs, we will allow them to proceed without hesitation.  Please encourage them to subscribe to our social media pages.  We will update these pages as developments and revisions are needed

Long's Paving has delivered letters to each home where the improvements will take place.  To see a copy of those letters, please click on the links below.

 

 

 

Weather Delay - June 16, 2023

 

Posted June 16, 2023 @ 1:21 PM

Franklin Township has been updated by our Contractor regarding our 2023 Road Program Schedule because of today’s storms.  As always, this schedule could fluctuate a day or two due to unforeseen weather- or job-related delays.  Please pass this information to anyone you know who may travel these roads.  Please be sure to subscribe to our social media pages.

Wednesday 6/21 – Start Milling on Old School House Road, Road Profiling and Shoulder Grading

Thursday 6/22 – Continue Milling on Old School House Road, Road Profiling and Shoulder Grading.

Friday 6/23 – Mill Hess Mill Road and start milling on Ways Run.  Continue Road Profiling and Shoulder grading on Old School House Road.

Saturday 6/24 – Mill Ways Run and Johnson Lane.  Continue Road Profiling and Shoulder Grading on Old School House Road.

Monday 6/26 – Pave Hess Mill Road and Install Leveling Course on Ways Run for Superelevation of section of Road.  Fine Grade Old School House Road areas that were re-profiled.

Tuesday 6/27 – Pave Ways Run and Johnson Lane.

Wednesday 6/28 – Shoulder and embankment grading Old School House Road.

Thursday 6/29 – Shoulder and embankment grading Old School House Road.

Friday 6/30 – Shoulder and embankment grading Old School House Road.

Monday 7/3 – Embankment seeding and netting.

Wednesday 7/5 Embankment seeding and netting.

Monday 7/10 – Pave Old School House Road.

Tuesday 7/11 – Pave Old School House Road.

Posted June 15, 2023

The Franklin Township 2023 Road Program starts the week of June 19th, 2023.  Please review the schedule below carefully.  It is important that you allow extra time into your daily schedules.   You will be inconvenienced while we improve these roads, and we are sorry.  Residents should plan on leaving their residence before the paving process starts if they must go out or plan on staying home for the day.  Work hours will start at approximately 7:00 AM and end at approximately 5:00 PM, Monday through Friday.  Using a single pass paver removes the cold joint (center seam) in the road, thus improving the longevity of the road.

 

Photo of Single Pass Paver - Example

We are asking that you please pass this information along to anyone you know who travels these roads.  This will include friends and family, your favorite delivery people, house cleaners, and trash companies.  Emergency Services (911) has been alerted to our schedule and if an emergency occurs, we will allow them to proceed without hesitation.

Long's Paving has delivered letters to each home where the improvements will take place.  To see a copy of those letters, please click on the links below.

We will update our social media pages as developments warrant. 

u know who travels these roads.  This will include friends and family, your favorite delivery people, house cleaners, and trash companies.  Emergency Services (911) has been alerted to our schedule and if an emergency occurs, we will allow them to proceed without hesitation.  Please encourage them to subscribe to our social media pages.  We will update these pages as developments and revisions are needed

Long's Paving has delivered letters to each home where the improvements will take place.  To see a copy of those letters, please click on the links below.

 

Schedule - Calendar of Events

2023 Tentative Road Schedule Program

  • Old School House Road - Entire road to be milled & paved.

  • Johnson Lane - Entire road to be milled & paved.

  • Ways Run - Entire road to be milled & paved.

  • Hess Mill Road - From New London Township line to eastern most entrance to Wingate Drive.

 

The dates mentioned above are subject to change, due to weather, equipment and materials.  Franklin Township encourages you to subscribe to our website and Facebook page for further updates.