Franklin Township, Chester County, PA

Township Administration

Tentative Roadwork Dates
  • June 7–8
  • Gypsy Hill Widening
  • June 9–14
  • Walker Road Drainage Improvements
  • June 15–23
  • Base Repair Work
  • June 27
  • Johnson Lane Overlay
  • Walker Road Overlay
  • June 28
  • Gypsy Hill Road Overlay
  • June 29
  • Pennbrook Drive Overlay
  • June 30
  • Church Hill Road Overlay

2011 Road Program

Road Program Update

InnConn, the road paving contractor, is working on swales and inlet repairs throughout the township. They are also excavating and widening Gypsy Hill Road. This work, along with the installation of the pipe underdrain on Walker Road, is expected to be completed by June 14.

InnConn has tentative plans to perform base repair work on the following roadways from June 15–23, starting with Church Hill Road and ending with Johnson Lane:

  • Church Hill Road - From the existing pavement seam approximately 500 feet west of the Church Hill Road Bridge to the existing pavement seam near the intersection of Creek Road
  • Pennbrook Drive - Entire length
  • Gypsy Hill Road - Entire length
  • Walker Road - From Appleton Road to Johnson Lane
  • Johnson Lane - Entire length

Once base repair work is completed they will go back through to do the overlay work, starting with Johnson Lane and ending with Church Hill Road.

Reminder: Residents in affected areas should clear roadways to be paved. This includes trimming back trees and shrubs overhanging roadways, as well as removing obstacles, such as vehicles, trailers, etc. (When trimming vegetation, there should be at least a 15-foot vertical clearance from the roadway and at least 2 feet of clearance from the edge of the pavement.)

Please do not hesitate to call us with questions.

Road Work Scheduled to Begin on June 6

Notice to Proceed for the 2011 Franklin Township Road Maintenance program was issued on May 25, 2011 with an effective date of May 26, 2011. The contract is for sixty (60) calendar days and therefore all work must be completed by July 25, 2011. Representatives from McCormick Taylor are in the process of completing all base repair and drainage repair markouts in the field.

The contractor is scheduled to mobilize on Monday, June 6, 2011. Work will begin with the drainage repair/swale construction and then continue with the paving operations. Notifications will be provided to residents who live on the effected roadways approximately one week prior to the start of work. An outline of the scheduled work to be completed will be posted to the website shortly.

Road Work Awarded to Innovative Construction Services (InnConn)

At the April 20, 2011 Board of Supervisors meeting, the Board voted to award the contract for this year's road work to Innovative Construction Services (InnConn).

Residents affected by planned road paving will be receiving a notice prior to the start of construction. Updates regarding the paving schedule will be posted here as they become available.

The following roads, or sections of roads, are scheduled to be included in the 2011 Franklin Road Paving Program.

Along with new blacktop, "base" repair will be made where needed. If you live on one of the above noted roadways, what you'll likely see first is a large grinding machine moving along and, in certain places that have been marked, cutting out 3 or so inches of the existing roadway surface. New "base type" blacktop will then be placed in those areas that have been cut out. After that, the whole roadway, or segment that's to be done in 2011, will receive an overlay of inch and a half or so of fresh paving material.

Residents in affected areas should clear roadways to be paved. This includes trimming back trees and shrubs overhanging roadways, as well as removing obstacles, such as vehicles, trailers, etc.

Also, please note that while roadways are not to be "closed," there will likely be delays.

*      *      *

In addition to paving, various improvements to roadside drainage infrastructure will also be occurring at non-specified times throughout the Township. This stormwater work includes occasionally replacing or adding piping that runs under the roadway, as well as improving roadside drainage. A final piece of this effort to manage stormwater is the repair and/or replacement of inlet boxes.

If there are any questions as the 2011 paving progresses, please call the Township office at 610-255-5212.


– Last updated June 8, 2011

Contact Us  |   Copyright ©2005–2012 Franklin Township, Chester County, PA. All rights reserved.